In an ERP programme, the interface layer is likely to outlive the migration itself. Companies that model customer and order data early, separate concerns and test each interface continuously can keep evolving while the core is replaced. Those that leave interfaces to the integrator tend to freeze for far longer than planned. Ownership of that layer is an executive decision.

This article draws on around six ERP programmes in which I served as CTO, CIO, fractional CTO or chief architect, across retail, manufacturing, wholesale, energy and construction, in companies with revenues between one and five billion. The examples are composites, with details changed.

Two programmes, one decision

Consider two companies of comparable size, both moving their core to S/4HANA. In the first, the programme froze most of the back office roadmap, together with every ecommerce feature that touched customer or order data. The freeze was presented as temporary; in practice it lasted about half as long again as planned.

The final months proved the most costly. Testing came late, rework accumulated and the teams worked through nights to protect the go live date. Under that pressure, the integrator bypassed tests to hold the plan, leaving the company with technical debt that its next programme will have to absorb.

The second company migrated a core of similar complexity. Its checkout, aftersales and omnichannel services nevertheless continued to evolve throughout, with only minor disruption, while the core was replaced beneath them.

Seen from the executive committee, the two programmes produced very different businesses:

Business impact

First programme

Second programme

Customer facing change

Checkout and aftersales frozen, for about half as long again as planned

Kept evolving through the migration, with minor disruption

Cutover

Late testing, rework and a high risk big bang

Contracts tested throughout, non regression in place before go live

What the company inherits

Technical debt from bypassed tests

A customer and order layer it can reuse for the next channel, partner or agent

  1. Late testing, rework and a high risk big bang

  2. Technical debt from bypassed tests

  3. Versus:

  4. Kept evolving through the migration, with minor disruption

Contracts tested throughout, non regression in place before go live

A customer and order layer it can reuse for the next channel, partner or agent

The interface layer is what the company keeps

Budgets were comparable, and so was the profile of the integrators. The difference lay in where leadership directed its attention. In the second company, the CIO, the CTO and the architects treated the interfaces as a strategic subject in their own right: what customer, order and product mean for the business, who has authority to change those definitions, and how each channel and system reaches them.

That choice changes what a programme leaves behind. The ERP core will be replaced again one day, just as it is being replaced now. A well modelled customer and order layer, with explicit interfaces and the tests that protect them, can outlast that replacement and the one after it. In that sense the interfaces are the programme: the migration is a moment in the company's history, while the interface layer is the asset it carries forward.

The pattern behind the overruns

The pressure behind these programmes is real and dated. Mainstream maintenance for SAP ERP 6.0 ends in 2027, with paid extended maintenance until 2030. Gartner data reported by The Register indicated that 39% of SAP's roughly 35,000 ECC customers had still not migrated at the end of 2024, which means a large part of the market is entering, or about to enter, the same kind of programme.

Overruns appear to be the rule. An ISG survey of 200 senior decision makers found that nearly 60% of SAP migration projects were delayed and over budget, and SAPinsider research puts the average S/4HANA deployment at around 18 months, with a quarter of projects expected to exceed two years.

Data is often where the delay begins. In a survey of more than 100 SAP customers and experts, conducted by a data migration vendor, 57% said data migration regularly delays their projects, and the recurring explanation was data addressed too late. This is the first programme seen from another angle: when the meaning of customer and order is only settled during the migration, every channel that depends on them has no choice but to wait.

Four choices that kept the second company moving

The first was to align data before anything moved. The company agreed a functional and data model for customer, order and product, independent of how any single system stored them, and made it the reference every interface had to respect.

The second was to separate concerns. Ecommerce and omnichannel were decoupled from the ERP through stable interfaces, so that the channels could keep changing while the back office was transformed. The coupling to the existing ERP was strong, as it usually is, but data modelling and well designed interfaces loosened it ahead of the migration.

The third was to test the contracts continuously. Each interface carried tests that ran with every change, so regressions surfaced within days of being introduced. Across more than ten programmes in which I have helped design the testing architecture, running it in parallel with the build is what made regular delivery possible first, then a faster cadence, with full non regression coverage in place before cutover.

The fourth was ownership. It would be easy to blame the integrator in the first company, yet that would miss the mechanism. An integrator held to a fixed date and price, with no one on the client side owning the interfaces, behaves rationally when it trims tests to protect the plan. In the second company, someone inside the business owned the contracts and treated every skipped test as a decision requiring their signature.

Figure 1. The interface layer is what the company keeps.

Figure 1. The interface layer is what the company keeps.

A steering role for the CTO and the CIO

Steering this layer typically falls to the CTO and the CIO, working with their architects, and it changes the nature of their role. Owning the interfaces means arbitrating between business priorities, programme constraints and the integrator's plan, and doing so in terms the executive committee recognises: which capabilities stay open during the migration, how much risk the cutover carries, and which options remain available once it is over.

This is a transformation role more than a delivery one, and it is increasingly what boards expect from technology leadership. A CTO or CIO who steers the interfaces sits where business stakes and technical choices meet, and becomes accountable for the outcomes the business expects, beyond the milestones of the programme.

Four signals a CEO can read

Four signals are usually enough to tell which of the two programmes a company is living, and none of them requires new tooling:

  • the number of business capabilities frozen until go live, and for how long;

  • the share of interfaces with a named business owner;

  • whether contract tests run with every change, or only before cutover;

  • the number of releases reaching production while the programme runs.

If the first figure keeps rising while the last remains at zero, the company is living the first programme, whatever colour the steering dashboard shows.

Decisions for this quarter, even mid programme

None of this requires waiting for the next migration. Every programme has to inventory and rework its interfaces in any case, so the real decision concerns how that work is framed, owned and funded.

In practice, it comes down to four decisions:

  • Appoint a business owner for the interface layer, with the CTO or CIO steering it and an architect accountable for its design.

  • Fund it outside the integrator's scope, so that it is not the first line to be cut when the plan slips.

  • Settle the model for customer and order before the next wave begins.

  • Make continuous contract tests a condition for each wave to start.

The same layer prepares the company for agents

The interface layer carries a further return, and it is arriving quickly. In November 2026, PwC told The Register that a clean core makes AI agents easier to deploy, and that budgets are now being split between ERP and AI. The same article noted that Kingfisher chose third party support for its existing ERP and built its AI strategy around that system with Databricks and Google. SAPinsider makes a similar point from within the SAP ecosystem, observing that S/4HANA programmes need clear integration patterns and data models that agents can use safely.

Whichever route a company takes, its agents will depend on the same foundation: well modelled, governed data behind explicit interfaces. A company that owns that layer can open it to agents whether or not its migration is complete. A company that does not will find its agents waiting on the same programme as everything else.

Holding the disciplines together

Having worked through these programmes from several seats, my conviction is that the interface question is rarely solved by any single discipline. It sits at the junction of enterprise architecture, application and data modelling, and quality engineering, with its testing strategy and automation. These are usually handed to separate teams, or left to the integrator. The second company did well largely because it held them together: the model defined what each interface meant, the architecture decided where the boundaries sat, and the testing strategy made every contract verifiable from the first wave.

AI now adds a fourth dimension. Applied across the delivery lifecycle, it can help inventory interfaces, map data between old and new models, and generate and maintain contract tests at a scale that used to be too costly, which may make decoupling mid programme far more affordable than it once was. It works on a governed model, however. Pointed at undefined interfaces, it tends to produce more change than the programme can safely absorb, a programme scale version of what I call the Absorption Gap.

The question to bring to the next steering committee is therefore a simple one: who owns our interfaces, and are they funded outside the programme?

Read further

FAQ

Is it too late to decouple if we are already mid migration?

Decoupling an ERP programme already in flight is usually still possible, because every migration has to inventory and rework its interfaces anyway. The cheapest moment is before the next wave: model customer and order, give the interfaces a business owner, and add contract tests. Capabilities already frozen may stay frozen, but the next ones need not be.

Doesn't a clean core strategy already solve this?

A clean core reduces customisation inside the ERP, which eases upgrades and, according to SAP and its partners, the deployment of AI agents. It does not by itself decide how channels, back office and partners exchange customer and order data. A clean core and a governed interface layer complement each other, and the interface layer is the part that can start before the core is clean.

Should the business or IT own the interfaces?

Interfaces carry business meaning, so a business owner should decide what customer and order mean and who may change those definitions. The CTO or CIO steers the layer as a whole, arbitrating between business priorities and programme constraints, with an architect accountable for how the interfaces are built. Leaving them entirely to the integrator places the contracts with the party under the strongest pressure to trade quality for schedule.

What does a contract test protect that end of programme testing does not?

A contract test checks, with every change, that an interface still behaves as agreed between the systems on each side of it. Testing at the end of a programme finds the same defects months later, when they are tangled with others and fixing them means rework under deadline. Running contract tests continuously is what lets a programme keep releasing during the migration and reach cutover with non regression already in place.

How does an interface layer prepare a company for AI agents?

AI agents act through interfaces: they read customer and order data and trigger changes through the same contracts as any other channel. A company with a well modelled, governed interface layer can give agents safe access whether or not its ERP migration is finished. Kingfisher's choice to build its AI strategy around its existing ERP suggests the migration itself is not the prerequisite; the data and the interfaces are.

Sources